HIGHLIGHTS
• Pinnacle maintains focus on technology and battery metals exploration
• 2024 to focus on “discoveries via the drill bit” with two drilling programs in planning phase over
Pinnacle’s project portfolio covering critical minerals including:
o
Lithium (Adina East – Quebec Canada)
o
Uranium & REE’s (Wirrulla – South Australia)
o
Mineral Sands / Ilmenite (Capel – Western Australia)
• Adina East Lithium Project exploration highlights:
o
LIDAR survey to identify potential pegmatite outcrops – Q2 2024
o
Field mapping and rock chipping identified targets – Q3 2024
o
Trenching / diamond drilling lithium targets – Q4 20241
• Wirrulla Uranium and Rare Earth Project exploration highlights:
o
XRF and assays of historical core to delineate REE targets – Q2 2024
o
Drilling permit (PEPR) lodged for Uranium drilling program
o
Drilling of uranium targets in regionally significant Narlaby Paleochannel – Q2/Q3 2024
• Capel Mineral Sands (Ilmenite) Project exploration highlights:
o
Drilling permit (POW) lodged and awaiting approval – April 2024
o
2,000m drilling program targeting ilmenite mineralisation planned - Q2 2024
• Pinnacle elects not to exercise Manna West option
Pinnacle Minerals Ltd (PIM:ASX) (“Pinnacle”, the “Company”) is pleased to release the Company’s 2024
exploration plan along with an accompanying corporate presentation. The Company’s 2024 exploration plan is
budgeted and fully funded from existing cash reserves and focuses on three projects targeting Lithium (Adina
East), Uranium (Wirrulla) and Heavy Mineral Sands (Capel), All commodities to be targeted fit with-in the critical /
technology minerals umbrella with the sequencing / timing of key exploration activities to provide consistent and
meaningful exploration results throughout the calendar year. To ensure project deliverables on key exploration
projects the company has elected to not exercise the Manna West option.
Pinnacle maintains a strong balance sheet and reaffirms its commitment to the Company’s flagship Adina East
Lithium Project in Québec Canada, the Wirrulla Uranium / REE Project in South Australia, and the Capel Mineral
Sands Project in Western Australia.
Pinnacle Minerals Managing Director, Nic Matich, commented:
“The Pinnacle team has spent the first quarter of the year planning and executing an exploration plan
involving several critical minerals at our priority projects. We have laid the foundations for success via
carefully composing our project portfolio in key commodities in tier 1 jurisdictions, all the while
maintaining a strong balance sheet and tight capital structure. Pinnacle is highly leveraged to success and
the team is excited about the exploration results that 2024 may bring”.
Pinnacle Minerals Ltd
Issued Capital
Australian Registered Office
Directors
ACN: 655 033 677
ASX: PIM
45,463,317 Shares
44,867,271 Options
Unit 6, Level 1, 389 Oxford Street
Mount Hawthorn WA 6016
T: + 61 8 9426 0666
E: admin@pinnacleminerals.com.au
WILLIAM WITHAM – Executive Chairman
NIC MATICH – Managing Director
LINCOLN LIU – Non-Executive Director
STEPHEN ROSS – Non-Executive Director
www.pinnacleminerals.com.au
Exploration Timeline 2024:
Adina East Lithium Project:
The Adina East Project is located in Québec’s James Bay region (Figure 1) with a total of 147 claims encompassing
72.7km2 (7,274.47 ha) overlying an interpreted extension of the Trieste greenstone belt. The Project is adjacent
to Loyal Lithium’s (ASX:LLI) Trieste project where spodumene-bearing dykes with intercepts including 31.8m at
2.2% Li2O5 have been drilled less than 6km from the boundary of the Project. Adina East is also adjacent to
Winsome Resources’ Tilly Project where swarming pegmatites have been mapped6 and are interpreted to extend
into the Adina East Project. The claims are readily accessible throughout the year from Mirage Outfitters and the
Renard diamond mine (75km to the northwest and 45km to the South of the Project respectively), with the
proposed La Grande Alliance eastern road mapped to pass through the Project.
The field season will begin in late May with a LIDAR survey of the entire project. High resolution orthophotos
taken simultaneously with the LIDAR readings will be draped over the digital elevation model (DEM), enabling the
identification of potential pegmatite outcrops which often show up as “evident” white elevated “areas”, as tested
by Pinnacle’s contractor on numerous other projects (Figure 2).
The results of the LIDAR program will be used to guide the summer field campaign scheduled to begin in midJuly. The field contractors have been engaged for 20-25 days (weather dependent), which is expected to be
sufficient time to map and take rock chip samples over the entirety of the project area.
The 2024 field season will follow on from the brief field campaign in October 2023 during which rock chip samples
returned significant rubidium enrichment, up to 658 ppm on a granitic pegmatite, indicative of magmatic
fractionation which is a precursor to lithium saturation. Importantly, key “fractionation ratios” of K/Rb below 100
over several samples (Figure 3) suggests the potential for a spodumene-bearing pegmatite to have been
generated, trending northwest into the project's metasedimentary rocks, like those that host Loyal Lithium’s
Trieste discovery (includes drilling intercepts of 40.0m at 1.2% Li2O1) 5 kms to the west.
www.pinnacleminerals.com.au
2
Figure 1: James Bay Province Highlighting Adina East Project Location.
Pegmatite outcrop
Figure 2: Example of successful identification of a pegmatite outcrop (ASX:MRZ - Bohier Project)
www.pinnacleminerals.com.au
3
Figure 3: K/Rb Ratios - Adina East
www.pinnacleminerals.com.au
4
Wirrulla Uranium and Rare Earth Project:
The Company awaits XRF and assay results of historical core across 53 holes from with-in the Narlaby
paleochannel. The holes selected are with-in both the Southern and Northern extents of the project where the
paleochannel has been mapped (Figure 4).
An application for a uranium and REE focused drilling program has been lodged, including a program for
environment protection and rehabilitation (PEPR) outlining a proposed 10-20-hole aircore drilling program and
subsequent rehabilitation plan. The drill program is designed to test for uranium mineralisation in a previously
undrilled section of the Narlaby paleochannel. The mines departments review of the application is expected to
be provided in Q2. Once approved, the Company will engage a local drilling contractor and schedule the program.
Figure 4: Wirrulla Project highlighting uranium mineralisation and targets
www.pinnacleminerals.com.au
5
Capel Mineral Sands Project:
The project was previously held by Tronox Limited (NYSE:TROX), a global, vertically integrated producer of
titanium dioxide and inorganic chemicals, with a US $2b market capitalisation.
Previous, regional-scale exploration, conducted in 2010 by Iluka Resources Limited, discovered moderate-grade
HM from surface on several drill lines. Pinnacle believes there is potential for defining cohesive mineralisation at
a more local scale, sufficient for delineating an appreciable mineral resource, within the tenement.
A ninety-three (93) hole drilling program (Figure 5) designed to test the continuity of the Ruabon beach placer
previously identified by Iluka has been designed and is pending approval of Program of Works (POW) applications
submitted in March 2024. The Company is anticipating the imminent approval of these applications. The c.2,000m
drilling program aims to define an ilmenite dominated heavy mineral resource.
Should the drill program successfully identify a mineral resource the Company will conduct a concept study,
which is a simplified Scoping Study. The results of the study will be used as a guide on whether the project has
development potential.
Figure 5: Capel Mineral Sands Project - Proposed Drill Collars
www.pinnacleminerals.com.au
6
Manna West Project:
The Company has reviewed assay results from the Manna West soil sampling program conducted in February
2024 and elected not to exercise the option to acquire the project. Whilst the assay results were encouraging,
they did not meet the rigorous standards set by the board to invest further in the project. All data pertaining to
the project is confidential and has been handed over to the tenement holders.
References:
1 – Pending successful field identification of spodumene bearing pegmatites
2 – Pending successful field identification of spodumene bearing pegmatites at Adina East
3 & 4 – Pending successful mineral sands drilling campaign
5 – Loyal Lithium Limited (ASX:LLI) ASX announcement 21st of March 2024
6 – Winsome Resources Limited (ASX:WR1) ASX announcement 19th of April 2023
This announcement has been authorised for release by the Board of Pinnacle Minerals Ltd.
For further information, please contact:
Executive Chairman
William Witham
Pinnacle Minerals Limited
T: + 61 (0) 8 9426 0666
E: admin@pinnacleminerals.com.au
Managing Director
Nic Matich
Pinnacle Minerals Limited
T: + 61 (0) 475 870 345
E: admin@pinnacleminerals.com.au
Media and Investor Inquiries
Jane Morgan
Jane Morgan Management
+61(0) 405 555 618
E: jm@janemorganmanagement.com.au
About Pinnacle Minerals
Pinnacle Minerals Ltd (ASX:PIM) is an ASX listed technology minerals company focused on delivering shareholder
value via the systematic exploration and development of its portfolio of battery and technology metals projects
in Canada, Western Australia and South Australia. Pinnacle aims to deliver exploration success via systematic
and geologically rigorous techniques. The Company’s focus is the “Adina East Project” in James Bay, Quebec which
is proximal to the world class Adina Lithium Project (Winsome Resources: ASX:WR1) and adjacent to the Trieste
Lithium Project (Loyal Lithium: ASX:LLI) and the Tilly Lithium Project (ASX:WR1). The Company’s Australian
exploration assets are prospective for Uranium, Rare Earth Elements, Mineral Sands and Kaolin.
Forward Looking Statements
This announcement contains ‘forward-looking information’ that is based on the Company’s expectations,
estimates and projections as of the date on which the statements were made. This forward-looking information
includes, among other things, statements with respect to the Company’s business strategy, plans, development,
objectives, performance, outlook, growth, cash flow, projections, targets and expectations, mineral reserves and
resources, results of exploration and related expenses. Generally, this forward-looking information can be
identified by the use of forward-looking terminology such as ‘outlook’, ‘anticipate’, ‘project’, ‘target’, ‘potential’,
‘likely’, ‘believe’, ‘estimate’, ‘expect’, ‘intend’, ‘may’, ‘would’, ‘could’, ‘should’, ‘scheduled’, ‘will’, ‘plan’, ‘forecast’,
‘evolve’ and similar expressions. Persons reading this announcement are cautioned that such statements are
only predictions, and that the Company’s actual future results or performance may be materially different.
Forward looking information is subject to known and unknown risks, uncertainties and other factors that may
cause the Company’s actual results, level of activity, performance, or achievements to be materially different
from those expressed or implied by such forward-looking information.
www.pinnacleminerals.com.au
7
Competent person statement
The information in this announcement that relates to Exploration Targets, Exploration Results, Mineral Resources
or Ore Reserves is based on information compiled by William Witham, a Competent Person who is a Member of
The Australian Institute of Geoscientists (AIG). William Witham is a director of Pinnacle Minerals Ltd. William
Witham has sufficient experience that is relevant to the style of mineralisation and type of deposit under
consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012
Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’.
William Witham consents to the inclusion in the presentation of the matters based on his information in the form
and context in which it appears.
Figure 6: Pinnacle Minerals Projects' Location Map
www.pinnacleminerals.com.au
8
Share your feedback
Discover