Wirrulla REE Project under application in South Australia
Released
Released
Announcement PDF
ASX Announcement
19 July 2023
Wirrulla REE Project under application in South Australia
HIGHLIGHTS
• Project centred on circular magnetic feature resembling a Mount Weld style intrusion currently
under application in Wirrulla, South Australia (ELA 2023-00031).
• Rare Earth Element (REE) potential:
o
o
Apatite > 10%, typical in carbonatites – CAR10-2 & CAR10-3
Pegmatites logged in CAR1-1
• Historical exploration by Diamond Ventures in 19951 (focussing on locating kimberlites)
identified Phosphorous between 2.3% and 3.74% P2O5
• Petrology report identified corresponding levels of apatite up to 15%, suggesting that the
original pre-metamorphic intrusive could have been of Ijolitic composition and may have
associated carbonatites
• Underexplored region with only four (4) drill holes reaching basement. The area has primarily
been explored for heavy mineral sands2,3,4 with numerous occurrences of pink – red clays (often
associated with REE’s)
Pinnacle Minerals Ltd (ASX: PIM) (“Pinnacle”, the “Company”) is pleased to announce that the Company has
applied for the Wirrulla Project (ELA 2023-00031). Historical exploration has indicated prospective Rare Earth
Element (REE) mineralisation in both hard rock (carbonatites) and clays.
The project is centred on a circular magnetic feature
that resembles a Mount Weld style intrusion where
historical exploration by Diamond Ventures on the
fringe of the structure identified levels of apatite
approaching 15% which is typical in carbonatites.
Additionally, a partly graphic granite pegmatite was
intercepted in historical drill hole CAR1-1 at a depth of
115.45m. No follow-up work was completed as the
primary target was Diamonds.
Whilst the application is under process, the Company
intends to conduct reconnaissance soil sampling over
areas of interest for benchmarking and delineating
new target areas.
Pinnacle Minerals Managing Director, Nic Matich, commented:
“The Wirrulla Project was applied for after an extensive review of historical data and is considered a
highly prospective target for both hard rock and clay hosted REE’s. The team is excited about the
potential of the project and will look to conduct first pass exploration this half to delineate potential
targets for follow up in H1 2024.”
Pinnacle Minerals Ltd
Issued Capital
Australian Registered Office
Directors
ACN: 655 033 677
ASX: PIM
36,375,200 Shares
29,937,634 Options
Unit 6, Level 1, 389 Oxford Street
Mount Hawthorn WA 6016
T: + 61 8 9426 0666
E: admin@pinnacleminerals.com.au
WILLIAM WITHAM – Non-Executive Chairman
NIC MATICH – Managing Director
LINCOLN LIU – Non-Executive Director
STEPHEN ROSS – Non-Executive Director
www.pinnacleminerals.com.au
Figure 1: Wirrulla Project highlighting circular magnetic structures and faults.
www.pinnacleminerals.com.au
2
References
1 – Open File Envelope Number 8981, EL 1952 Carawa, Annual and final report for the period 27/7/94 to
22/11/95
2 – Open File Envelope Number 11094, Els 3163, 3201, 3202, 3267, Iluka Resources Annual Technical Reports
for the period 01/07/2004 to 16/06/2016
3 – Open File Envelope Number 8230, EL 1605, BHP Minerals, Final Report for the period 18/08/1989 to Dec
1991
4 – Open File Envelope Number 4010, Carpentaria Exploration, Combined Quarterly reports for the period
1979 to 1983
This announcement has been authorised for release by the Board of Pinnacle Minerals Ltd.
For further information, please contact:
Managing Director
Nic Matich
Pinnacle Minerals Limited
T: + 61 (0) 8 9426 0666
E: admin@pinnacleminerals.com.au
Media and Investor Inquiries
Jane Morgan
Jane Morgan Management
+61(0) 405 555 618
E: jm@janemorganmanagement.com.au
About Pinnacle Minerals
Pinnacle Minerals Ltd (ASX: PIM) is an ASX listed technology minerals company focused on delivering
shareholder value via the systematic exploration and development of its portfolio of kaolin, halloysite, battery
metals and Heavy Mineral Sands prospective projects in Western Australia and South Australia. The Company
is focused on delineating resources at its Bobalong and Holly Kaolin Projects in the Great Southern region of
Western Australia whilst simultaneously expanding its’ project portfolio through targeted acquisition of
prospective ground. Drilling and a scoping study have been completed at Bobalong, with results indicating the
potential for a high value direct shipping ore (DSO) product. The White Knight and Camel Lake Projects are
strategically located adjacent to Andromeda Metals’ (ASX: ADN) high-grade kaolin-halloysite discoveries in
South Australia. The Latham and Tammin projects are adjacent to Chalice Mining Ltd (ASX: CHN) Mid-West
Project and Anglo Americans’ (LON: AAL) Southwest Yilgarn Exploration Project respectively, which have multielement exploration potential.
Competent person statement
The information in this announcement that relates to Exploration Targets, Exploration Results, Mineral
Resources or Ore Reserves is based on information compiled by William Witham, a Competent Person who is
a Member of The Australian Institute of Geoscientists (AIG). William Witham is a director of Pinnacle Minerals
Ltd. William Witham has sufficient experience that is relevant to the style of mineralisation and type of deposit
under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the
2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves’. William Witham consents to the inclusion in the presentation of the matters based on his information
in the form and context in which it appears.
www.pinnacleminerals.com.au
3
Figure 2: Pinnacle Minerals Projects' Location Map
Appendix 1 Collar Summary – Referenced Drill Holes
Easting
Northing
Hole ID
(AMG Zone
53H)
(AMG Zone
53H)
CAR10-1
CAR10-2
449545
449525
6410125
6410227
CAR10-3
449443
6410435
CAR1-1
CAR2-1
437896
441956
6425317
6419574
www.pinnacleminerals.com.au
RL
EOH
(m)
(m)
-
25.9
33.4
-
128.6
51.7
49
Orientation
Vertical
Vertical
60° towards
90° magnetic
Vertical
Vertical
4
Appendix 2 JORC Tables
Section 1 Historical Sampling Techniques and Data
Criteria
JORC Code explanation
Sampling
techniques
•
•
•
•
Drilling
techniques
•
Nature and quality of sampling (e.g., cut channels, random chips,
or specific specialised industry standard measurement tools
appropriate to the minerals under investigation, such as down
hole gamma sondes, or handheld XRF instruments, etc.). These
examples should not be taken as limiting the broad meaning of
sampling.
Include reference to measures taken to ensure sample
representivity and the appropriate calibration of any
measurement tools or systems used.
Aspects of the determination of mineralisation that are Material
to the Public Report.
In cases where ‘industry standard’ work has been done this would
be relatively simple (e.g., ‘reverse circulation drilling was used to
obtain 1m samples from which 3 kg was pulverised to produce a
30 g charge for fire assay’). In other cases, more explanation may
be required, such as where there is coarse gold that has inherent
sampling problems. Unusual commodities or mineralisation
types (e.g., submarine nodules) may warrant disclosure of
detailed information.
Drill type (e.g., core, reverse circulation, open-hole hammer,
rotary air blast, auger, Bangka, sonic, etc.) and details (e.g., core
diameter, triple or standard tube, depth of diamond tails, facesampling bit or other type, whether core is oriented and if so, by
what method, etc.).
Commentary
•
•
•
•
•
Drill sample
recovery
•
•
•
Logging
•
•
•
Sub-sampling
techniques and
sample
preparation
•
•
•
NQ diamond core was used to
obtain samples for analysis at
1m intervals
Strata Exploration Pty Ltd
conducted the drilling
NQ diamond core was used to
obtain samples for analysis at
1m intervals
Diamond core drilling is
considered a standard industry
technique for hard rock drilling
NQ diameter (76mm) drill bits
and rods were used
Method of recording and assessing core and chip sample
recoveries and results assessed.
Measures taken to maximise sample recovery and ensure
representative nature of the samples.
Whether a relationship exists between sample recovery and grade
and whether sample bias may have occurred due to preferential
loss/gain of fine/coarse material.
Whether core and chip samples have been geologically and
geotechnically logged to a level of detail to support appropriate
Mineral Resource estimation, mining studies and metallurgical
studies.
Whether logging is qualitative or quantitative in nature. Core (or
costean, channel, etc) photography.
The total length and percentage of the relevant intersections
logged.
•
Meter-by-meter basis of
sampling is not expected to
alter the interpretation of the
results.
•
The diamond core samples
If core, whether cut or sawn and whether quarter, half or all core
taken.
If non-core, whether riffled, tube sampled, rotary split, etc., and
whether sampled wet or dry.
For all sample types, the nature, quality and appropriateness of
the sample preparation technique.
•
www.pinnacleminerals.com.au
were each qualitatively logged
by the onsite geologist.
•
The samples were logged
quantitively as being
representative of hole
lithology
1/2 core samples were cut. No
further details on sample
handling are available.
•
5
Criteria
JORC Code explanation
•
•
•
Quality of
assay data and
laboratory tests
•
•
•
Verification of
sampling and
assaying
Location of
data points
•
•
•
•
•
•
•
Quality control procedures adopted for all sub-sampling stages
to maximise representivity of samples.
Measures taken to ensure that the sampling is representative of
the in-situ material collected, including for instance results for
field duplicate/second-half sampling.
Whether sample sizes are appropriate to the grain size of the
material being sampled.
The nature, quality and appropriateness of the assaying and
laboratory procedures used and whether the technique is
considered partial or total.
For geophysical tools, spectrometers, handheld XRF instruments,
etc., the parameters used in determining the analysis including
instrument make and model, reading times, calibrations factors
applied and their derivation, etc.
Nature of quality control procedures adopted (e.g., standards,
blanks, duplicates, external laboratory checks) and whether
acceptable levels of accuracy (i.e., lack of bias) and precision have
been established.
The verification of significant intersections by either independent
or alternative company personnel.
The use of twinned holes.
Documentation of primary data, data entry procedures, data
verification, data storage (physical and electronic) protocols.
Discuss any adjustment to assay data.
Accuracy and quality of surveys used to locate drill holes (collar
and down-hole surveys), trenches, mine workings and other
locations used in Mineral Resource estimation.
Specification of the grid system used.
Quality and adequacy of topographic control.
Commentary
•
•
•
All results were reviewed by
the Competent Person
•
Data points were taken from
Open File Envelope Number
8981, EL 1952 Carawa, Annual
and final report for the period
27/7/94 to 22/11/95
CRS utilised was AMG Zone
53H, local grids established
using a Ensign GPS and 99
reading average. Drill collars
located on local grids.
•
Data spacing
and
distribution
•
•
•
Data spacing for reporting of Exploration Results.
Whether the data spacing and distribution is sufficient to
establish the degree of geological and grade continuity
appropriate for the Mineral Resource and Ore Reserve estimation
procedure(s) and classifications applied.
Whether sample compositing has been applied.
•
•
•
Orientation of
data in relation
to geological
structure
•
•
Whether the orientation of sampling achieves unbiased sampling
of possible structures and the extent to which this is known,
considering the deposit type.
If the relationship between the drilling orientation and the
orientation of key mineralised structures is considered to have
www.pinnacleminerals.com.au
Petrological examinations
were made on representative
samples from the core
samples by Dr. Jane Barron.
The sample from drillhole
CAR10-1, 25.8m was also
examined by J.Stiefenhofer
from AARL (Pty) Limited.
Assays were performed by
Australian Laboratory
Services (ALS) using the IC587
method, Au was assayed by
the PM201 method.
•
The drilling program was
conducted to test magnetic
targets for the presence of
diamond mineralisation
No mineralisation was
intersected
Drill logs reviewed for
presence of indicator
minerals and samples
submitted for indicator
mineral analysis.
Drill holes were primarily
vertical as the aim of the
campaign was to test
basement material to vector
in on diamond occurrences
6
Criteria
JORC Code explanation
introduced a sampling bias, this should be assessed and reported
if material.
Commentary
•
•
1m meter samples
aresufficient to define
basement material
The orientation of the drilling
is considered appropriate for
testing the basement material
Sample security
•
The measures taken to ensure sample security.
•
Unknown security of samples
Audits or
reviews
•
The results of any audits or reviews of sampling techniques and
data.
•
No independent audits or
reviews of sampling
techniques and data has been
conducted.
Section 2 Reporting of Exploration Results
(Criteria listed in the preceding section also apply to this section.)
Criteria
JORC Code explanation
Mineral
tenement and
land tenure
status
•
•
Exploration
done by other
parties
•
Commentary
Type, reference name/number, location and ownership including
agreements or material issues with third parties such as joint ventures,
partnerships, overriding royalties, native title interests, historical sites,
wilderness or national park and environmental settings.
The security of the tenure held at the time of reporting along with any
known impediments to obtaining a licence to operate in the area.
•
Acknowledgment and appraisal of exploration by other parties.
•
•
•
•
Geology
•
Deposit type, geological setting and style of mineralisation.
www.pinnacleminerals.com.au
•
Historical drilling within
the granted exploration
licence ELA 250-93- .
At the time of reporting
Pinnacle has applied for
ELA 2023-0003 which
encompasses all drill
collars referenced in this
release
Diamond Ventures
explored for diamonds
targeting magnetic
anomalies thought to
represent kimberlites.
Diamond drill core from 8
targets was assessed by
petrology and
geochemistry.
National Mineral Sands
(1989-91), Peko
Exploration (1991-1992),
BHP (1989-1992) and
Iluka (2005-2016) all
explored the area for
Heavy Mineral Sands.
Carpentaria (1981-83)
explored for sedimentary
uranium.
Basement rocks are the
Archean Sleaford
Complex of the Gawler
Craton consisting of
metamorphosed granites,
mafic volcanics and
gneisses. The Archean
7
Criteria
JORC Code explanation
Commentary
rocks are overlain by
remnant units of the
Eocene and/or Miocene
littoral marine sediments
of the Eucla and Polda
Basins.
Drill hole
Information
•
•
Data
aggregation
methods
•
•
•
Relationship
between
mineralisation
widths and
intercept
lengths
•
Diagrams
•
Balanced
reporting
•
Other
substantive
exploration
data
•
Further work
•
•
•
A summary of all information material to the understanding of the
exploration results including a tabulation of the following information
for all Material drill holes:
o easting and northing of the drill hole collar
o elevation or RL (Reduced Level – elevation above sea level in metres)
of the drill hole collar
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.
If the exclusion of this information is justified on the basis that the
information is not Material and this exclusion does not detract from
the understanding of the report, the Competent Person should clearly
explain why this is the case.
In reporting Exploration Results, weighting averaging techniques,
maximum and/or minimum grade truncations (e.g., cutting of high
grades) and cut-off grades are usually Material and should be stated.
Where aggregate intercepts incorporate short lengths of high-grade
results and longer lengths of low-grade results, the procedure used for
such aggregation should be stated and some typical examples of such
aggregations should be shown in detail.
The assumptions used for any reporting of metal equivalent values
should be clearly stated.
These relationships are particularly important in the reporting of
Exploration Results.
If the geometry of the mineralisation with respect to the drill hole angle
is known, its nature should be reported.
If it is not known and only the down hole lengths are reported, there
should be a clear statement to this effect (e.g., ‘down hole length, true
width not known’).
Appropriate maps and sections (with scales) and tabulations of
intercepts should be included for any significant discovery being
reported. These should include, but not be limited to a plan view of
drill hole collar locations and appropriate sectional views.
Where comprehensive reporting of all Exploration Results is not
practicable, representative reporting of both low and high grades
and/or widths should be practiced to avoid misleading reporting of
Exploration Results.
Other exploration data, if meaningful and material, should be reported
including (but not limited to): geological observations; geophysical
survey results; geochemical survey results; bulk samples – size and
method of treatment; metallurgical test results; bulk density,
groundwater, geotechnical and rock characteristics; potential
deleterious or contaminating substances.
The nature and scale of planned further work (e.g., tests for lateral
extensions or depth extensions or large-scale step-out drilling).
www.pinnacleminerals.com.au
•
•
All significant drill results
and drill hole collar
locations have been
identified in Appendices 2
and 3 respectively of this
report.
No relevant material data
has been excluded from
this report.
•
There are no data
aggregation methods
applied
•
No mineralised widths
and intercept lengths
have been reported.
•
Figures and plans are
displayed in the main
text of the Release
•
Reporting of historical
rock chips which were
selected randomly
•
All information has been
provided as available
•
Reconnaissance soil
sampling over areas of
interest for benchmarking
8
Criteria
JORC Code explanation
•
Diagrams clearly highlighting the areas of possible extensions,
including the main geological interpretations and future drilling areas,
provided this information is not commercially sensitive.
Commentary
•
•
•
www.pinnacleminerals.com.au
and delineating new
target areas.
Drilling to target potential
carbonatite and kaolinite
mineralisation.
Exploration by
geophysical analysis and
drilling is planned on
other parts of the
tenement.
Refer to the main body of
the release for further
information regarding
diagrams
9
Share your feedback
Discover